Project Start Date: Sat 01/27/01
Project Finish Date: Fri 02/02/01
ID | Name | Duration | Start | Finish | Actual Start | Actual Finish | Acutal Duration | Duration Variance |
---|---|---|---|---|---|---|---|---|
1 | Remove some parts | 6 hrs | Sat 01/27/01 | Sat 01/27/01 | NA | NA | 0 hrs | 6 hrs |
2 | Remove rear side glass | 3 hrs | Sat 01/27/01 | Sat 01/27/01 | NA | NA | 0 hrs | 3 hrs |
3 | Cut header above windshield | 4 hrs | Sat 01/27/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
4 | Cut through rear quarter panels and rear floor | 4 hrs | Sat 01/27/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
5 | Trim rear frame horns | 4 hrs | Mon 01/29/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
6 | Install gas filler neck | 3 hrs | Mon 01/29/01 | Tue 01/30/01 | NA | NA | 0 hrs | 3 hrs |
7 | Trial fit rear body section | 5 hrs | Tue 01/30/01 | Tue 01/30/01 | NA | NA | 0 hrs | 5 hrs |
8 | Install B-pillar cross braces | 4 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 4 hrs |
9 | Install rear body section | 5 hrs | Wed 01/31/01 | Wed 01/31/01 | NA | NA | 0 hrs | 5 hrs |
10 | Fit trunk lid | 3 hrs | Wed 01/31/01 | Thu 02/01/01 | NA | NA | 0 hrs | 3 hrs |
11 | Install trunk latch | 2 hrs | Thu 02/01/01 | Thu 02/01/01 | NA | NA | 0 hrs | 2 hrs |
12 | Install sport bar, fit seat belts and inner panels | 3 hrs | Wed 01/31/01 | Thu 02/01/01 | NA | NA | 0 hrs | 3 hrs |
13 | Install battery box in rear | 4 hrs | Sat 01/27/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
14 | fit tonneau and door seal | 4 hrs | Wed 01/31/01 | Thu 02/01/01 | NA | NA | 0 hrs | 4 hrs |
15 | Install window-tracking mechanizm in door | 4 hrs | Sat 01/27/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
16 | Cut door window frame and fit A-pillar piece | 4 hrs | Mon 01/29/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
17 | Fit door caps | 3 hrs | Mon 01/29/01 | Tue 01/30/01 | NA | NA | 0 hrs | 3 hrs |
18 | LH windshield wiper set-back | 2 hrs | Sat 01/27/01 | Sat 01/27/01 | NA | NA | 0 hrs | 2 hrs |
19 | Trim front frame horns | 3 hrs | Mon 01/29/01 | Tue 01/30/01 | NA | NA | 0 hrs | 3 hrs |
20 | Install hood latches | 2 hrs | Tue 01/30/01 | Tue 01/30/01 | NA | NA | 0 hrs | 2 hrs |
21 | Install hinge bar, hang nose, and attach 1/4 panels | 4 hrs | Tue 01/30/01 | Tue 01/30/01 | NA | NA | 0 hrs | 4 hrs |
22 | Install new radiator, hoses, fan and switch | 4 hrs | Sat 01/27/01 | Mon 01/29/01 | NA | NA | 0 hrs | 4 hrs |
23 | Fit grille | 3 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 3 hrs |
24 | Fit rocker covers | 5 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 5 hrs |
25 | Fit headlight buckets | 3 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 3 hrs |
26 | Install trunk finishers and ABS windshield header finisher | 3 hrs | Thu 02/01/01 | Thu 02/01/01 | NA | NA | 0 hrs | 3 hrs |
27 | Fit top | 3 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 3 hrs |
28 | Fit hood scoop | 2 hrs | Tue 01/30/01 | Wed 01/31/01 | NA | NA | 0 hrs | 2 hrs |
29 | Final assembly | 8 hrs | Thu 02/01/01 | Fri 02/02/01 | NA | NA | 0 hrs | 8 hrs |